The rehabilitation project was required to address reliability issues related to age and to improve safety standards.

Photo credit: NJ Transit


Project Details

The project involved rehabilitation of both the north and south tubes; concrete replacement of the brick liner in the north tube as well as new concrete direct fixation track. Additionally, the design provided for a new positive flow drainage system with tunnel life safety upgrades such as lighting, ventilation, and emergency egress. Upon completion, only the Bergen Tunnel’s north tube was constructed and featured waterproofed ceilings and walls; new electrical, signal and ventilation systems; new emergency exits; a new concrete floor; and new tracks affixed directly to the concrete floor.

Role & Responsibility

Ashoka Consulting LLC staff served as the deputy project manager and administered and coordinated railroad and utility force account work to ensure contractual, plan, schedule and cost compliance on this project. Also coordinated track outages for the consultant for geotechnical program study and was responsible for assisting in the development of an Environmental Assessment (EA) including Section 106 and Section 4(f) documentation and preparation of Memorandum of Agreement (MOA).


Services
  • Project Management
  • Contract Administration
  • Project Controls
  • Railroad Force Account
  • Utility Force Account
  • Project Reports Development
  • Cost Estimating
  • Cost Management / Controls
  • Schedule Management / Controls
  • Payment Request Review

*This project represents independent experience of staff from Ashoka Consulting LLC while a member of a previous firm and/or agency.